Louisiana Public Service Commission General Order dated 09-19-2019. This Order memorializes the Commission's revised Net Metering Rules for solar customers. Decided at the September 11, 2019 Business and Executive Session.
Pursuant to the Commission's General Order dated September 19, 2019 ("Distributed Generation Rules"), customers who submit an interconnection request and/or install a distributed generation facility after December 31, 2019 shall pay the full retail rate for all energy purchased from the utility, shall pay a zero rate for all energy self-generated and consumed, and shall be credited at Avoided Cost for the energy sold back to the utility.